Front-end wafer cleanrooms, advanced packaging, compound semi. Renka has been on site in the EU semiconductor cluster for over 15 years - in Saxony, in the Po Valley, in Crolles, in the Brainport region. With live-fab experience, not just greenfield construction. Current focus is the EU Chips Act pipeline.
Three active mega projects. 110 km from Jablonec.
The EU Chips Act pipeline is more concentrated in 2026 than the headlines suggest. Intel Magdeburg halted. ST/GF Crolles deferred. Wolfspeed Ensdorf frozen. What is actually being built sits within a few kilometres of Dresden:
- ESMC Dresden - TSMC joint venture with Bosch, Infineon and NXP. Tool move-in H2 2026.
- Infineon Smart Power Fab Dresden - 300mm power semi, production start 2026.
- GlobalFoundries Dresden - SPRINT project, EUR 1.1bn capacity expansion, groundbreaking March 2026.
Three active mega projects, together around EUR 16 bn of investment, all inside the Silicon Saxony cluster around Dresden. Renka is 110 km away in Jablonec - site management and standing crew can be on site the same day. At the Dresden wafer sites Renka crews have worked repeatedly over the past 15 years (details in the section below).
15 years of continuous cluster presence.
Where Renka crews have been repeatedly on site across the five European semiconductor clusters over the past 15 years. Location, scope and timeframe are open - end-client mapping is in the prequalification dossier under NDA.
Dresden, Freiberg
Continuous presence at Dresden wafer sites since the early 2010s. Additional front-end work in Freiberg - wafer and logistics cleanrooms.
Grenoble cluster
Cleanroom and HVAC mechanical work in the Grenoble cluster (2011-2015). Cleanroom expansions during live wafer production, tool hookup experience.
Catania, Agrate, Avezzano
Front-end cleanrooms and HVAC in Catania, Agrate and Avezzano (2010-2018). Classic power and mixed-signal semi.
Eindhoven, Nijmegen, Schiphol, Dublin
Cleanroom and HVAC experience at semiconductor sites in Eindhoven, Nijmegen, Schiphol and Dublin (2013-2020).
Premstätten, Villach
Cleanroom mechanical work in Premstätten and Villach (2012-2018). Mixed-signal and power management, ISO 5 manufacturing.
Leuven (B)
Cleanroom and HVAC mechanical work in Leuven (2015-2020). Pilot lines for sub-7-nm processes.
Geographic overview of the semiconductor clusters where Renka crews were repeatedly on site between 2010 and 2024. Specific end-client names and project details exclusively in the prequalification dossier - under NDA.
What we deliver at a wafer fab.
- Front-end cleanrooms ISO 14644-1 Class 1-5 with laminar airflow 0.36-0.54 m/s
- Sub-fab HVAC, AHU assembly, pressure cascade connection including validation
- AMHS integration (automated material handling systems)
- Chase areas and tool hookup during scheduled maintenance windows
- UPW, bulk gas and chemical supply lines (orbital TIG)
- Shutdown retrofit within the shutdown window with FOD discipline
- IQ/OQ support, particle count to ISO 14644-3, as-built drawings
Who is on the client list.
From the confirmed end-client list of the last 15 years: 9 of the top 12 EU semiconductor names, including leading wafer manufacturers, front-end IDMs, foundries and specialist manufacturers for compound and power semi. Specific names exclusively in the prequalification dossier.
Request client listRequest semiconductor capability sheet.
ISO class matrix, tool hookup experience, AMHS references, mobilisation lead times.